PROJECT DESCRIPTION
The Demolition of Parker Center Project is the first phase of a multi-year Los Angeles Civic Center Master Plan, which includes the construction of the new Los Angeles Street Civic Building (see rendering). Due to the Parker Center’s close proximity to City Hall, the City identified the re-activation of this underutilized site as a way to maximize and consolidate city services. The Parker Center, once home to the Los Angeles Police Department, is located at 150 N. Los Angeles Street and has been vacant since 2013.
The Demolition of the Parker Center Project will include removal of the building, the foundations, utility tunnels and related activities. The project will also include relocation of utilities, re-route of fiber optic network, and installation of duct banks to bundle and protect buried cables (electrical, fiber optics, etc.), which are needed to support future development. The project also includes a graded, temporary excavation road plate, a temporary maintenance ramp, security fencing and lighting.
Low Impact Development Best Management Practices will be employed during demolition to limit the effects on the surrounding community and environment. All construction debris will be removed from the site by the contractor, Silverado Constructors. Future development of the site will move forward following demolition.
The project’s Environmental Impact Report (EIR) process began in 2008 and was approved by the City Council in March 2017. Demolition of the site began in June 2018 and will be completed at the end of 2019.
PROJECT HOTLINE - 1-888-840-2610
If you have questions or concerns about the Demolition of Parker Center Project, please call the Project Hotline at 1-888-840-2610
- - Available to answer demolition-related questions and comments
- - Available in English, Japanese, Korean, and Spanish
- - Staff will respond within 48 hours
ENVIRONMENTAL IMPACT ANALYSIS
The demolition of the Parker Center is part of the construction of the Los Angeles Street Civic Building. The final EIR for the overall project can be viewed here: https://eng2.lacity.org/techdocs/emg/docs/LA_Street_Civic_Bldg_Final_EIR_Nov_2016.pdf
COMMUNITY OUTREACH
Demolition of Parker Center Project Informational Meeting
Thursday July 26, 2018
4:00 p.m. JACC Garden Room
Businesses and other stakeholders in the project area were invited to meet with Councilmember Jose Huizar’s staff and the Bureau of Engineering’s project team to discuss the impacts of demolition, mitigation measures and overall project timeline.
The presentation to stakeholders can be viewed here: Parker Center Demo Info Meeting 07262018
VIDEO BY COUNCILMEMBER JOSE HUIZAR (CD14)
Learn more about the Civic Center Master Plan in this video with Councilmember Jose Huizar: VIDEO