The CEQA review begins by determining if a proposed project is subject to CEQA regulations, as various exemptions apply. When a project is exempt or not subject to CEQA, the lead agency can file a notice of exemption. For non-exempt projects, the lead agency may conduct an initial study to evaluate potential significant environmental impacts. This study serves as a preliminary evaluation rather than a comprehensive assessment like an Environmental Impact Report (EIR), helping the agency decide whether an EIR or a negative declaration is warranted.
Depending on the initial study's findings, the environmental document type is selected as follows:
- Environmental Impact Report (EIR): Required when substantial evidence indicates that the project may cause a significant environmental impact.
- Negative Declaration: Prepared if there is no substantial evidence of significant environmental effects, or if project modifications eliminate potential significant impacts identified in the initial study.
- Mitigated Negative Declaration: Prepared when the initial study identifies potential significant effects, but conditions of approval incorporate mitigation measures that lower all impacts to a less-than-significant level.
Ultimately, projects subject to CEQA typically undergo review by the Board of Public Works (BPW) and/or the City Council, which hold the authority to approve the project as submitted, approve it subject to conditions, or deny approval.
Environmental Management Division CEQA Publications
The CEQA documents posted here are designed to foster public involvement and awareness regarding public works and related projects. However, they do not replace formal, legally required publications or reviews. While every effort is made to ensure that all information is accurate and updated promptly, no liability can be accepted for damages resulting from any errors.
Note: Adobe Acrobat Reader version 4.0 or later is required to view and print PDF files. Download a free copy now if it is not already installed on your system.
Written comments must be submitted during public review periods via one of the following methods and RECEIVED prior to the close of the review window:
- Mail: City of Los Angeles, Department of Public Works, Bureau of Engineering, Environmental Management Division, 1149 S. Broadway, Suite 600, Los Angeles, CA 90015-2213
- Fax: (213) 847-0656
- Email: A specific project email address will be supplied alongside each project listing.
Agenda items for the Board of Public Works, Council committees, City Council, and other commissions are published online 72 hours before each public meeting. You can access up-to-date schedules and meeting information using the links below:
- Board of Public Works: Use this link to view the schedule/agenda of the Board of Public Works meetings.
- Council and Committee Calendar: Use this link to find the schedule of city council and council committee meetings.
- Council File Index: Use this link to view reports submitted to the city council and the record of council actions.
City Hall is located at 200 North Spring Street, with the main public entrance on Main Street. Both the City Council chambers and the Board of Public Works hearing room can be found on the third floor.